D.C. Airport Expansion Moves Ahead in Phases

Land has always been a valuable asset for Washington Dulles International Airport. During the decades since the first flights departed from architect Eero Saarinen’s distinctive main terminal in November 1962, the federally owned airport’s approximately 12,000-acre tract in northern Virginia has provided ample room to grow in step with the region’s demand for air travel. The Metropolitan Washington Airports Authority, which operates Dulles, reports that in 2025, it handled more than 29 million passengers, more than one-third of which were for international flights.

With passenger growth expected to continue, the authority is putting that space advantage to work with a recently expanded $20-billion airport capital investment program that includes new and modernized concourses, expansion of the AeroTrain automated people mover system and addition of a fifth runway.

While the program is expected to unfold during the next 15 years, Dulles has immediate needs to maintain operating efficiency for its tenant airlines while accommodating the continuing crush of travelers. An important step will be realized this fall as the Turner Construction/PGAL design-build team completes the initial 14-gate, 435,000-sq-ft phase of Concourse E—boosting capacity for United Airlines international and domestic flights.

Dulles International Airport

The Metropolitan Washington Airports Authority is overseeing a $20-billion program at Dulles International Airport to modernize concourses, expand the automated people mover system and add a fifth runway.
Rendering courtesy PGAL

The $745-million project includes the region’s first Multiple Aircraft Ramp System gates, each able to serve a single wide-body or two narrow-body planes at the same gate. An elevated corridor will direct arriving international passengers making connecting flights to a Federal Inspection Service area to be constructed as part of Concourse E’s second phase, while shuttles transport those staying in Washington to the airport’s International Arrivals Building.

Concourse E also will provide more than 44,000 sq ft of shopping, dining and other passenger amenities, a 40,000-sq-ft United Club and sustainability features such as high-efficiency climate control systems and support for electric vehicles to service aircraft and carry passengers.

“It’s transformational,” Dulles’ airport manager Richard Golinowski told visitors on a June press tour of the facility. “It gives customers a new opportunity to enjoy the airport and improves safety, operations, security and building systems with minimal environmental effects.”

Multiple Aircraft Ramp System

The project includes the region’s first Multiple Aircraft Ramp System gates, each able to serve a single wide-body plane or two narrow-body planes at the same gate.
Photo courtesy Turner Construction

Step-by-Step Strategy

While Concourse E’s initial phase has yet to handle a commercial flight, its future is already on the drawing board. HOK is currently designing a two-phase expansion totaling 1.1 million sq ft as well as a new central utility plant. Earlier this year, Turner was awarded the Phase 2 construction manager at-risk contract, which the authority hopes to begin in 2027.

Agency project manager Chris Beausoleil explains that building out Concourse E in phases rather than constructing the long-planned facility in its entirety, centers around the facility’s environmental approval process.

“The expansion is based on our current and projected growth, so we have a fairly aggressive schedule to build out,” Beausoleil says. “We received approval for the first phase and proceeded with construction while starting the design process on the next two phases. Phase 2 should reach the 60% stage in January, and enabling work is already underway to clear buildings for construction.”

While Concourse E’s initial phase may be smaller than the typical major airport passenger facility upgrade project, it still presents the challenges of safely carrying out construction on an active airfield.

“The expansion is based on our current and projected growth.”

—Chris Beausoleil, Project Manager, Metropolitan Washington Airports Authority

“We’re surrounded by active taxi lanes and a runway to the east, so planes are always traversing around us,” says Turner construction executive Derek Brown. Along with coordinating deliveries and other logistics with the authority, identifying laydown areas and securing Federal Aviation Administration approval for crawler cranes, the team also needed to get its workforce credentialed and approved by airfield security each day. “That took a lot of up-front effort with our subs,” he adds.

Mirroring the hectic airfield environment was the multifaceted effort to prepare the site for construction. Utilities serving the active underground AeroTrain station, located three stories below Concourse E’s apron level, had to be carefully coordinated to keep the system in operation. In addition, an existing 20-ft by 30-ft airfield tunnel was extended by 370 ft to bring main airport utilities into the new concourse.

Utility design was still in progress when Turner began installing more than 140 caissons, each 30-in. to 60-in.-dia and as deep as 60 ft, through the underlying shale rock. Brown says that by taking advantage of caissons’ relatively small footprint, “we could design and permit the foundation package prior to having all underslab utilities coordinated. That freed up underground space for the new line routings and helped get new construction underway.”

Another early challenge was incorporating the AeroTrain station into the Concourse E structural system and cutting openings into the concrete “lid” for new stairs and escalators without damaging existing post-tension tendons.

“The new concourse columns sit directly atop the existing station columns so that the load path goes directly to the bedrock underlying the station,” Brown says. “The existing roof slab was carefully scanned to identify the location of all post-tensioned cables prior to laying out and constructing the concrete plinths that would support the new steel building columns.”

Brown adds that caissons adjacent to the station were drilled and placed without excavation to avoid compromising the station’s waterproofing envelope or affecting its structural integrity. The station’s envelope was also modified to incorporate an existing electrical substation.

crawler cranes

Operating within Federal Aviation Administration-specified limitations, crawler cranes were used on Concourse E’s two-level steel frame and curtain wall.
Photo courtesy Turner Construction

Prefabrication Plays a Role

By comparison, Concourse E’s vertical and interior construction have proceeded smoothly, with contractors installing 5,200 tons of structural steel and 95,000 sq ft of unitized curtain wall. Beausoleil credits the design-build project team’s close cooperation for keeping the project on track for an on-budget, on-schedule completion—an impressive feat in a period when many key construction materials are in high demand.

“We factored material escalation into subcontractor pricing prior to negotiation of our final price and agreed on early procurement of major equipment to lock in the prices, ensuring that it was here on time,” Beausoleil says.

“The new concourse columns sit directly atop the existing station columns so that the load path goes directly to the bedrock underlying the station.”

—Derek Brown, Construction Executive, Turner Construction

Brown admits that securing a sufficient workforce has been a challenge, particularly given the spate of data center construction activity in the MidAtlantic region and beyond. Combining virtual design and construction technology with early trade coordination and offsite prefabrication has helped maintain the project’s schedule while reducing the number of workers needed on site.

“In the design phase, we looked for big building components that we could preassemble,” he says, adding that up until the last few months of construction, there were no pipe-bending or threading machines on site.

“Mechanical and electrical subassemblies came out and it fit right in,” Brown says. “For interior components such as bulkheads, soffits and ceiling features, we set up areas on site to mass-produce that framing.”

Brown adds that the construction team worked hard to retain trade talent by going the extra mile to make Concourse E a good place to work, providing amenities such as a climate-controlled break and lunch room with tables and microwave..

Securing workers “has still been a challenge, but it hasn’t impacted the schedule,” Brown says, adding that the project has mostly been free of unexpected complications. “It’s been the usual—not enough people, not enough hours, a lot of rain and a couple of snows,” he says. “But we keep pushing along.”

Concourse E

While Concourse E’s initial phase may be smaller than the typical major airport passenger facility upgrade project, it still presents challenges of safely carrying out construction on an active airfield.
Photo courtesy Turner Construction

Flight Plan for the Future

Meanwhile, the airports authority and Turner prepare for Concourse E’s second phase—with enabling work such as relocating airline cargo staging lots, glycol mixing and storage facilities for airline deicing as well as a new hardstand area for aircraft parked overnight. With both the second and third phases set to be in service by 2031, the agency already plans another midfield concourse. By then, Beausoleil says, it can begin gradual decommissioning of Dulles’ existing Concourse C/D, which was built as a temporary facility in the mid-1980s.

Brown says those projects and others planned as part of the Dulles expansion program will benefit from the same approach Turner has taken with Concourse E.

“You can’t over-communicate enough because there are so many stakeholders involved in a project like this,” he says. “We worked hard not to have surprises, and all that planning and communication really helped.”

Golinowski considers the project a huge success for Dulles’ immediate and long-term goals.

“We’re giving our customers more space and more opportunities to enjoy and relax as they travel through the airport,” he says. “The expansion and transformation of the airport is just beginning.”