Escalation: Predicting project costs in a volatile market

Jun 3, 2024 | Public | 0 comments

One of the major hurdles that we attempt to forecast for our commercial construction projects is escalation. There are many factors that affect escalation in the construction world which include inflation, supply chain, and labor shortages. Predicting costs eliminates potential cost escalation and avoids stress throughout projects.

There are several reputable industry cost indexes that measure the construction market to help predict construction escalation. These commercial cost indexes including TurnerConsumer Price Index, and CBRE, have ranged a cost increase between 10% to 14% from January 2022 to this year’s end. It is important to be aware of cost escalation implications that have taken place in the last couple of years and what our industry is forecasting.

In addition to commercial cost indexes, we can talk with local contractors and use our own historical cost data from previous projects, to better understand how the market has been behaving and to make an educated guess as to what escalation percentage will be needed to include for the future.

How can we control costs in a volatile market?

  1. Order Early
  2. Early Construction Packages
  3. Continuous Cost Analysis

Order Early

“Currently, 77% of work order delays are attributable to unavailable materials. Standardize purchasing and your equipment configuration. Forward-buy critical spares and manage inventory. Engage with your suppliers to understand their dependencies and delivery risks (Facilities Management Cost Trends 2022, CBRE).” By encouraging facilities to order materials prior to building, project costs can significantly decrease and surprises late in the game can be avoided.

Facilities Management Cost Trends 2022, CBRE
Photo courtesy Design Collaborative

Early Construction Packages

Engaging a construction manager (CM) with the team early in the design process, allows for materials to be secured in the beginning stages. With materials and construction packages determined at the start, costs are less likely to change, projects are more likely to stay on budget, and cost estimations are more accurate.

Early Construction Packages
Photo courtesy Design Collaborative

Continuous Cost Analysis

Throughout the life of a project, but particularly in the design process, it is imperative to continually analyze project costs. It’s important to check costs not just at major milestone estimates including Conceptual, Schematic, Design Development and Construction Documents, but throughout the entire design. Preparing for add and deduct alternates is essential; add alternates are preferred with contractors being more aggressive to do more work. Additionally, it is important to identify long lead times to keep projects on track.

Continuous Cost Analysis
Photo courtesy Design Collaborative

There is no rule of thumb that can predict how the market is going to change. But with factual, statistical information we can help validate cost prediction and expect what is to come for our next project.

The post "Escalation: Predicting project costs in a volatile market" appeared first on Building Design & Construction

0 Comments

Submit a Comment

Groundbreaking School Security Standard Protects Students During Active Shootings

In the wake of the tragic rise in active shooter incidents at schools, the National Glass Association (NGA) took swift...

Upping the IAQ in your building

Allergens and dust are found in the air throughout the summer, so IAQ remains a priority year-round. Maintenance managers...

Businesses Bet Big on Data Analytics and Integrated Worktech

In today’s hybrid work landscape, organizations are striving to strike the perfect balance between boosting operational...

Initiative seeks to close emergency response gaps

Asleep in bed, the sound of sirens outside your condo awakens you in the middle of the morning. You hear no alarm and no...

Gen Z Can Fill the Workforce Gap

We may have done a disservice to the Gen Z group of young people. Facility management professionals often label them as...